Rock Blasting: By the Numbers

Completed: Fall 2013

Our rock blasting for the new bed tower on Clifton Road is complete! Here are some neat facts about how far we've come with the project.

  • To date, we have hauled away 14,334 truckloads of bedrock, which equals about 143,343 cubic yards of soil.

  • The total quantity of blasted rock through July 2013 is 13,150 cubic yards.

  • The project averaged more than 200 trucks per day when material is being removed, with some days reaching 280 trucks per day for hauling out material.